Kalanga Gad Hydroelectric Project (15.33MW)
Client: Kalanga Hydro Private Limited
Type of Work: All Construction Work
Kalanga Gad Hydro Electric Project of 15.33 MW capacity, is a run-of-river type project located in Sunkuda and Khiratadi VDCs of Bajhang district of Seti Zone of Far – Western Region of Nepal. The description of various aspects of the project including climatic conditions, hydrology, sedimentology, geology, of the project site etc.
Salient Features |
Units of work completed |
% Complete |
Remarks |
Headworks |
100% |
|
|
Concrete |
14,248 cum |
|
|
Rebar |
1,091 ton |
|
|
Formwork |
28,632 Sq. m. |
|
|
Headrace Tunnel |
|
|
|
Size |
3.6 m x 3.8 m |
|
|
Length |
3,468 m |
|
|
Underground Excavation |
49,260 cum |
100% |
|
Rock Bolt |
17,794 Nos. |
|
|
Shotcrete |
57,880 Sq. m |
|
|
Concrete |
2,614 cum |
|
|
Surge Shaft |
100% |
|
|
Size |
6.8m dia x 18.75m height |
|
|
Excavation |
1,328 cum |
|
|
Penstock |
100% |
|
|
Length |
354m |
|
|
Powerhouse/Tailrace |
95% |
|
|
Powerhouse Size |
40.6m (L) x 21.8m (B) x 18.75m (H) |
|
|
Concrete |
4,652 cum |
|
|
Rebar |
577 ton |
|
|
Formwork |
11,422 sq. m |
|
|
|
|||
Total Concrete |
23,872
cum |
|
|
Total Rebar Used |
2,098
ton |
|
|
Total Formwork |
4,44,430
sq.m |
|
|